Long range road plans for Long Lost Lake Township
YEAR GRAVELING cost SPRAYING cost SPECIAL PROJECTS cost
2005 Complete graveling $20,621 None $0 None $0
2006 None $0 None $0 Advisory speed signs $120
Beaver pond leveler $425
Culvert extensions $1,400
Brushing $6,300
2007 Spot graveling $2,157 Spring spraying $937 Road repair, Big Hill/Seaberg $4,500
2008 Complete graveling $20,600 Fall spraying $1,616 Curve markers, McKenzie Road $236
2009 Spot graveling $0 Spring spraying $1,868  Two McKenzie road improvements $1,985
Logging damage, McKenzie/Chimney $530
2010 Spot graveling $0 None $0 Big Hill road work (by Glanders Lake Trl) $540
Remove exposed rocks in roadbed and $1,485
block logging road-McKenzie/Chimney
2011 Complete graveling $21,000 None $0 Seaberg/Lake crossing $1,820
Spot graveling shared $1,100
2012 Spot graveling $0 Spring spraying $1,814 Seaberg/highline, low spot $910
McKenzie/Peninsula (south curve) $5,160
2013 Spot graveling $480 None $0 Sign replacement $805
Seaberg Brushing $1,500
2014 Complete graveling $24,835 None $0 Dead tree removal from road ROW $1,200
Moving road edges $500
2015 Spot graveling Spring or Fall spraying
2016 Spot graveling as needed
2017 Spot graveling as needed
2018 Complete graveling as needed